Saadiyat Bridge, Abu Dhabi |
Execution period |
September 2007 - May 2008 |
Product |
Ø32 mm BB Bar, Grade 930/1080
Ø36 mm BB Bar, Grade 930/1080
Ø40 mm BB Bar, Grade 930/1080
and specific Components
|
Quantity |
Bars 51.65 MT |
Contractor |
Ed. Zueblin AG |
Client |
Tourism Development & Invest. Co. |
Design |
Parsons International Limited |
|
|
|
Execution period |
February 2008 - April 2008 |
Product |
Barex 63.5 mm, Grade 555/700
|
Quantity |
248 MT |
Contractor |
Leader Civil Engineering Corporation Ltd. |
Client |
MTR Corporation Limited |
Design |
Atkins China Ltd. |
|
|
|
Execution period |
September 2007 - February 2008 |
Product |
Ø20 mm RTA Rock Bolt,
Double Corrosion Protection
|
Quantity |
6,565 Each |
Contractor |
Leighton Contractors and Baulderstone Hornibrook Bilfinger Berger Joint Venture |
Client |
Rivercity Motorway/Brisbane city Council |
Design |
- |
|
|
|
Tai Po Mini Piles, Hong Kong |
Execution period |
September 2007 - November 2007 |
Product |
Mini Piles, Ø63.5 mm Barex Bar Grade 555/700
Couplers and Lock Nuts
|
Quantity |
Bars 212.40 MT |
Contractor |
China Harbor Engineering Co Ltd. |
Client |
DSD |
Design |
- |
|
|
|
Skansenloepet Tunnel, Trondheim |
Execution period |
January 2007 - March 2007 |
Product |
Ø50 mm Barex Bar, Grade 500/625
and specific Components
|
Quantity |
Bars 306 MT |
Contractor |
Bilfinger Berger Special Foundation |
Client |
Statens Vegvesen |
Design |
Bilfinger Berger Foundation Engineering |
|
|
|
|
|
|